By resolution passed via ballot, the five nominees referenced below were appointed as Directors of the Company to serve until the next annual meeting of shareholders of the Company, or until their successors are elected or appointed.  The results of the ballot were as follows:

Name of Nominee Votes For Percent Votes Withheld Percent
Peeyush Varshney 50,810,549 99.76% 112,420 0.24%
Marco Strub 50,931,969 100.00% 1,000 0%
Praveen Varshney 50,790,549 99.72% 142,420 0.28%
John Thomas 50,931,969 100.00% 1,000 0%
Xinfu Hu 50,931,969 100.00% 1,000 0%

Shareholders also voted to approve the re-appointment of Davidson & Company LLP as auditors of the Company.

The Akie Zn-Pb-Ag Project

The 100% owned Akie property is situated within the Kechika Trough, the southernmost area of the regionally extensive Paleozoic Selwyn Basin and one of the most prolific sedimentary basins in the world for the occurrence of SEDEX zinc-lead-silver and stratiform barite deposits.

Drilling on the Akie property by ZincX Resources since 2005 has identified a significant body of baritic-zinc-lead SEDEX mineralization known as the Cardiac Creek deposit. The deposit is hosted by siliceous, carbonaceous, fine grained clastic rocks of the Middle to Late Devonian Gunsteel Formation.

The Company updated the estimate of mineral resources for the Cardiac Creek deposit in late 2017 based on additional drilling completed in 2017, as follows:

5% Zinc Cut-Off Grade Contained Metal
Category Tonnes
(million)
Zn (%) Pb (%) Ag (g/t) Zn (B lbs) Pb (B lbs) Ag
(M oz)
Indicated 22.7 8.32 1.61 14.1 4.162 0.804 10.3
Inferred 7.5 7.04 1.24 12.0 1.169 0.205 2.9
 
Parameter Base Case1
Tonnes Mined 25.8 Mt
Mined Head Grades 7.6% Zn; 1.5% Pb; 13.08 g/t Ag
Tonnes Milled 19.7 Mt
Milled Head Grades (after DMS2 upgrade) 10.0% Zn; 1.9% Pb; 17.17 g/t Ag
Total Payable Metal (LOM) $3,960M3
Initial CAPEX $302.3M including $45.7M contingency
LOM Total CAPEX $617.9M including $58.5M contingency
All-in Total OPEX $102.4 per tonne milled
Pre-Tax NPV7% $649M
Pre-Tax IRR 35%
Pre-Tax Payback 2.6 years
After-Tax NPV7% $401M
After-Tax IRR 27%
After-Tax Payback 3.2 years

The Company announced robust positive results from the 2018 Preliminary Economic Assessment (PEA). The PEA envisages a conventional underground mine and concentrator operation with an average production rate of 4,000 tonnes per day. The mine will have an 18-year life with potential to extend the life-of-mine (LOM) through resource expansion at depth. Key parameters for the PEA are as follows:

1. The base case used metal prices are calculated from the 3 year trailing average coupled with two year forward projection of the average price; and are: US$1.21/lb for zinc, US$1.00/lb for lead and US$16.95 for silver. A CDN$/US$ exchange rate of 0.77 was used. The NPV discount rate is 7%. 2. DMS = dense media separation. 3. All dollar amounts expressed in Canadian dollars.

The PEA is considered preliminary in nature and includes mineral resources, including inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Mineral resources that are not mineral reserves have not yet demonstrated economic viability. Due to the uncertainty that may be attached to mineral resources, it cannot be assumed that all or any part of a mineral resource will be upgraded to mineral reserves. Therefore, there is no certainty that the results concluded in the PEA will be realized.

Kechika Regional Project

In addition to the Akie Project, the Company owns 100% of eight of eleven large, contiguous property blocks that comprise the Kechika Regional Project including the advanced Mt. Alcock prospect. The Kechika Regional Project also includes the Pie, Yuen and Cirque East properties within which the Company maintains a significant 49% interest with partners Teck Resources Limited (TSX: TECK.B) and Korea Zinc Co. Ltd. These properties collectively extend northwest from the Akie property for approximately 140 kilometres covering the highly prospective Gunsteel Formation shale; the main host rock for known SEDEX zinc-lead-silver deposits in the Kechika Trough of northeastern British Columbia. These projects are located approximately 260 kilometres north northwest of the town of Mackenzie, British Columbia, Canada.

Ken MacDonald P.Geo., Vice President of Exploration for the Company, is the designated Qualified Person as defined by National Instrument 43-101 and is responsible for the technical information contained in this release. Mike Makarenko P.Eng, JDS Energy and Mining, is the designated Qualified Person as defined by National Instrument 43-101 and is responsible for the PEA technical information contained in this release.

The TSX Venture Exchange has neither approved nor disapproved the contents of this press release.

ON BEHALF OF THE BOARD OF DIRECTORS

ZINCX RESOURCES CORP.

“PEEYUSH VARSHNEY”

                                                           

PEEYUSH VARSHNEY, LL.B
CEO & CHAIRMAN

02.27.2024

ZincX Resources to Participate at PDAC 2024 Conference

arrowRead More
12.14.2023

ZincX Resources Reports Voting Results from its Annual General Meeting

arrowRead More
11.30.2023

ZincX Resources to Hold Annual General Meeting on December 7, 2023

arrowRead More

arrowView All News

Stay up to date with our latest news:

What are you searching for?